Paver Calculator: How Many Pavers, Gravel & Sand Do I Need?

A paver project is four purchases, not one: the pavers themselves, the crushed-stone base, a one-inch sand bed, and polymeric sand for the joints. Enter your patio dimensions, paver size, and laying pattern below and this tool figures all four — pavers rounded up with typical pattern waste, and base/sand tonnages labeled as estimates. No sign-up, no tracking: the math runs entirely in your browser.

By HowMuchBuild Editorial TeamCalculation reviewedUpdated October 2026

ft

in

ft

in

length ″

width ″

Nominal size — e.g. a 4″×8″ paver is the most common patio paver.

Waste figures are typical — more cuts and curves mean more waste.

4″ is standard for patios and walkways; 6″ for driveways.

Estimated cost

What will it cost?

Enter your local store prices — prices vary by region.

  • Pavers

    594 pavers

    —

  • Gravel base

    2.4 tons

    —

  • Bedding sand

    0.6 tons

    —

  • Polymeric sand (50-lb bags)

    2 bags

    —

Estimate — prices vary by store and region. Check your local store for current pricing.

You need

594pavers

Includes 10% waste (Running bond) · patio area 120 sq ft

2.4

tons · gravel base (est.)

0.6

tons · bedding sand (est.)

2

bags · 50-lb poly sand (est.)

How we calculated it

  1. Patio area = 12 ft × 10 ft = 120 sq ft
  2. One paver covers 8″ × 4″ ÷ 144 = 0.22 sq ft
  3. Raw paver count = 120 ÷ 0.22 = 540
  4. With 10% waste (Running bond, typical) = 540 × 1.1 = 594 → round up = 594 pavers
  5. Gravel base = 120 sq ft ÷ 100 × (4″ ÷ 2″) = 2.4 tons (estimate)
  6. Bedding sand = 120 × 1″÷12 = 10 cu ft = 0.37 cu yd × 1.4 = 0.52 tons (estimate)
  7. Polymeric sand = 120 sq ft ÷ 80 = 1.5 → round up = 2 fifty-lb bags (estimate)
PaversBedding sand — 1″Crushed-stone base — 4″ (patios) / 6″ (driveways)Compacted soilRunningbondstaggered joints

Material estimates for planning. Gravel and sand tonnage is an estimate — bulk density varies by supplier, stone type, and moisture. Always round up and confirm loads with your supplier.

Worked example: 12×10 ft patio, 4×8 in pavers, running bond

The classic backyard patio. Here is the full arithmetic, step by step:

  1. Area: 12 ft × 10 ft = 120 sq ft
  2. One paver: 8″ × 4″ ÷ 144 = 0.2222 sq ft
  3. Raw count: 120 ÷ 0.2222 = 540 pavers
  4. With 10% waste (running bond, typical): 540 × 1.10 = 594 → 594 pavers
  5. Gravel base (4″): 120 ÷ 100 × (4 ÷ 2) = 2.4 tons — estimate
  6. Bedding sand: 120 × (1″ ÷ 12) = 10 cu ft = 0.37 cu yd; 0.37 × 1.4 = 0.52 tons — estimate
  7. Polymeric sand: 120 ÷ 80 = 1.5 → round up = 2 fifty-lb bags — estimate

Paver coverage chart

Pavers needed per 100 sq ft before waste — add your pattern's allowance on top:

Paver sizeArea per paverPavers per 100 sq ft
4″ × 8″0.222 sq ft450
6″ × 6″0.25 sq ft400
6″ × 9″0.375 sq ft267
8″ × 8″0.444 sq ft225
12″ × 12″1.0 sq ft100

Materials for common projects

Using 4×8 in pavers, running bond (10% waste), and a 4-inch base. Gravel and sand figures are estimates:

ProjectPaversGravelBedding sandPoly sand
10×10 ft patio (100 sq ft)4952.0 tons0.5 tons2 bags
12×16 ft patio (192 sq ft)9513.9 tons0.9 tons3 bags
4×20 ft walkway (80 sq ft)3961.6 tons0.4 tons1 bag

The formulas

Patio area

A = Length × Width (rectangle) or A = π × r² (circle) — all in feet.

Paver count

Pavers = ⌈ A ÷ ((paver L″ × paver W″) ÷ 144) ⌉ with waste: ⌈ raw × 1.05 / 1.10 / 1.15 ⌉ for stack bond, running bond, or herringbone (typical figures).

Gravel base tonnage (estimate)

Tons = (A ÷ 100) × (base depth in inches ÷ 2) — from the rule that 1 ton covers roughly 100 sq ft at 2 inches deep. Bulk density varies by supplier and moisture, so treat this as a planning figure.

Bedding sand tonnage (estimate)

Tons = (A × 1″ ÷ 12) ÷ 27 × 1.4 — the 1-inch sand bed in cubic yards, converted at roughly 1.4 tons per cubic yard.

Polymeric sand bags (estimate)

Bags = ⌈ A ÷ 80 ⌉ — one 50-lb bag per 80 sq ft, a common rule of thumb that varies with joint width and paver size.

Frequently asked questions

How many pavers do I need for a 10×10 patio?

A 10×10 ft patio is 100 sq ft. With standard 4×8 in pavers (0.2222 sq ft each), that's 450 pavers before waste — 495 with the typical 10% running-bond allowance.

How much waste should I plan for with different paver patterns?

As typical guidance: about 5% for stack bond (grid, few cuts), 10% for running bond (offset, the most common), and 15% for herringbone (zigzag, most cuts). Curves and border cuts push all of these higher.

How deep should the gravel base be under pavers?

4 inches of compacted crushed stone is standard for patios and walkways; use 6 inches for driveways. Deeper bases handle heavier loads and freeze-thaw movement better.

How much sand goes under pavers?

A 1-inch layer of coarse bedding sand over the compacted gravel base. It's screeded flat — not compacted — then the pavers are set and vibrated into it.

How many tons of gravel do I need per 100 sq ft of patio?

Using the rule of thumb that 1 ton covers about 100 sq ft at 2 inches deep, a 100 sq ft patio at a 4-inch base depth needs about 2 tons of gravel — but this is an estimate, since bulk density varies by supplier and moisture.

How much polymeric sand do I need for my paver joints?

Roughly one 50-lb bag per 80 sq ft of pavers is a common rule of thumb — an estimate that varies with joint width and paver size. The calculator above rounds the count up for your area.

Can I lay pavers directly on dirt or existing concrete?

Not directly on dirt — without a compacted gravel base and bedding sand, pavers settle unevenly within a season or two. Laying over an existing concrete slab is possible with edge restraints and good drainage, but that changes the whole build-up; treat it as guidance and check local best practice.

Base depth: patios vs. driveways

The base is what keeps pavers from heaving and settling — most paver failures are base failures, not paver failures. Four inches of compacted crushed stone suits patios and walkways; step up to six inches where cars park or turn. Compact the base in two-inch lifts with a plate compactor rather than dumping all the stone at once. The one-inch sand bed goes on top of the compacted base, is screeded flat, and is not compacted before the pavers go down.